A3 block Photovoltaic System (423 kWp)

Lyon Electric-Renewable Energy Sources

General facts

Description & main goal

Installation of a Photovoltaic system on the roof of aa new building (A3 block).

Deployment area
Lyon Confluence
Involved actors and their role

SPL Lyon-Confluence (Policy maker)

ICADE (Real Estate Developer)

Transénergie (PV system developer)

Key-contact person
Main challenges & risks
  • Delay in the installation
  • Change of the PV system features
  • No connection with the data platform
Delivery date
M24

Specific facts

Main challenges & risks

Connection of the Photovoltaic installation  to the Lyon Métropole data platform.

Delivery date

March 2018

Main challenges & risks
  • Delay in the installation
  • Change of the PV system features
  • No connection with the data platform
Implementation status

In which phase is the project (Planning, Implementation, Operation or Evaluation)?
Implementation
What is the current implementation status/ what is the current activity step?
Construction of this block on-going
Is the implementation process on time or are there any derivations? Please outline any changes and reasons.
On time
Which project steps were performed since the last project reporting?
Start of construction: April 2015
Building permit: Mars 2015
Selection of the real estate developer: February 2013

Have there been changes regarding the planned solution? Please outline any changes and reasons.
No

Complete 80%
Next steps & To Do ́s

Please shortly outline the next steps planned for the implementation of the project.
- Finalisation of the construction of this block
- Construction of this PV system
- Connection to the Grand-Lyon data platform
Are there additional steps planned due to occurred challenges? Which corrective activities have been taken?
No