Girard Hall / H7 Photovoltaic System (243 kWp)

Lyon Electric-Renewable Energy Sources

General facts

Description & main goal

Installation of a Photovoltaic system on the roof of a refurbished building : Girard Hall / H7

Category
Refurbishment of an office building
Deployment area
Lyon Confluence
Involved actors and their role

SPL Lyon Confluence (owner of the photovoltaic installation)

Key-contact person
Main challenges & risks

To finance the PV system - Necessity to obtain a feed-in tariff within national auctions for PV - To make sure that that the actual energy performance of the refurbished building will match initial expectations - To select a company that will be in charge of operation this building.

Delivery date
M20

Specific facts

Delivery date

September 2018

Main challenges & risks

To finance the PV system - Necessity to obtain a feed-in tariff within national auctions for PV - To make sure that that the actual energy performance of the refurbished building will match initial expectations - To select a company that will be in charge of operation this building.

Connection of the Photovoltaic installation  to the Lyon Métropole data platform.

Main challenges & risks

To finance the PV system - Necessity to obtain a feed-in tariff within national auctions for PV - To make sure that that the actual energy performance of the refurbished building will match initial expectations - To select a company that will be in charge of operation this building.

Complete 100%
Next steps & To Do ́s

Data-based monitoring of the photovoltaic production, thanks to the communication infrastructure, and the data sharing agreement signed between the city data platform and the owner of the photovoltaic installation.