Linky Smart Meters in Lyon-Confluence

Lyon Data management platform & smart services

General facts

Description & main goal

Deploy electric smart meters solution called Linky in the Lyon-Confluence area. 8,000 smart meters are planned. The objective is to monitor the actual effects and benefits on the electric grid, of energy-related measures implemented.

Category
Infrastructure
Deployment area
Lyon Confluence
Involved actors and their role

Enedis (electric grid operator)

 

Grand Lyon (data platform operator)

Key-contact person
Main challenges & risks
  • Respect the delay in the installation of smart meters
  • Difficulty in getting the explicit consent of consumer to share their consumption data,
  • Setting-up of the API between Enedis and Grand-Lyon and quality of the data exchange
Delivery date
M18

Specific facts

Main challenges & risks
  • Respect the delay in the installation of smart meters
  • Difficulty in getting the explicit consent of consumer to share their consumption data,
  • Setting-up of the API between Enedis and Grand-Lyon and quality of the data exchange
Complete 45%
Implementation status

Operation phase

Complete 100%
Next steps & To Do ́s

Data-based monitoring of the electric grid, thanks to the communication infrastructure of the Linky electric smart meters, and the data sharing agreements signed between the city data platform, the eletric grid operator (Enedis) and the data owners.