Implementation status
In which phase is the project (Planning, Implementation, Operation or Evaluation)?
Implementation phase
What is the current implementation status/ what is the current activity step?
The building permit for the construction phases 1 and 2 does exist. (1 – demolition of the four container classes, open spaces for sports and district heating by pass; 2 – underground construction; 3 – building itself)
Phase 1 is finished; Phase 2 is running.
The street on one side of the school area (Greifgasse) was closed – partly for construction equipment, partly as open spaces for pupils.
Is the implementation process on time or are there any deviations (time wise)? Please outline any changes and reasons.
The finalisation of the whole project (gym and school extension) is planned for August 2019 and it will be in operation from September 2019 on.
Which project steps were performed since the last project reporting?
Detailed technical concept for Zero-Energy-Gym was developed with all preparation works;
Have there been changes regarding the planned solution? Please outline any changes and reasons.
The gym will be underground, partly under the extension building, partly under open areas. This enables a larger amount of open spaces for the pupils and sports areas at ground level are more high-grade than on the roof of the gym (as previously planned in the preliminary concept). Another advantage is that the break courts aren´t in the inner courtyard anymore but on open spaces behind the building. Therefore, the noise problem is solved.